AND AWAY WE GO …
Five years of planning, funding approval and away we go.
The Seismic Replacement of PRMS started January 2025, with early works including the removal
of the band room, temporary road access, sewer line upgrade, playground removal and soil
removal. In the late spring 119 piles and pile caps were installed. Fall and Winter the
underground sewer lines, rebar and concrete was poured for the slab on grade.
The old house in front of the new school was purchased by the School District to accommodate
for the main electrical service entering the building.
In December the steel structure arrived for the multi purpose room and gym. These were
erected just before Christmas.
More posts and pictures to follow.